Minister Gwede Mantashe announces 5th Bid Window of Renewable Energy IPP Procurement Programme (REIPPPP Bid Window 5)

Signing of Preferred Bidder projects under the 5th Bid Window, and announcement of Preferred Bidders under the 6th Bid Window of the REIPPPP

The Minister of Mineral Resources and Energy is pleased to announce that an additional thirteen (13) projects under the 5th Bid Window of the Renewable Energy IPP Procurement Programme (REIPPPP Bid Window 5) have signed legal agreements on 8th December 2022, paving the way for additional new generation capacity to come on-line from early 2025. The Minister also announced the Preferred Bidders appointed under the REIPPPP Bid Window 6.

REIPPPP Bid Window 5

The Minister and Eskom concluded the Power Purchase Agreements (PPAs) and Implementation Agreements (IAs) with the thirteen projects at a signing ceremony held at in Centurion. The projects will all be procured from Solar PV technologies at project unit sizes of 75MW each and will contribute an additional 975MW renewable energy to the national grid.

The projects that have signed legal agreements on 8th December 2022 are as follows:

Project Name

Main Developer

Location

Grootfontein PV 1

Scatec

Touwsriver Western Cape

Grootfontein PV 2

Scatec

Touwsriver Western Cape

Grootfontein PV 3

Scatec

Touwsriver Western Cape

Grootspruit Solar PV

Engie – Pele Consortium

Allenridge,Free State

Graspan Solar PV

Engie – Pele Consortium

Ritchie,Northern Cape

Sannaspos Solar PV Pr

Engie – Pele Consortium

Botshabelo, Free State

Du Plessis Dam Solar PV 1

Total Mulilo

De Aar, Northern Cape

Kentani Solar Facility

Ikamva Consortium

Dealesville, Free State

Project Name

Main Developer

Location

Klipfontein Solar Facility

Ikamva Consortium

Dealesville, Free State

Klipfontein 2 Solar Facility

Ikamva Consortium

Dealesville, Free State

Leliehoek Solar Facility

Ikamva Consortium

Dealesville, Free State

Braklaagte Solar Facility

Ikamva Consortium

Dealesville, Free State

Sonoblomo Solar Facility

Ikamva Consortium

Dealesville, Free State

Once all Conditions Precedent (CPs) have been met and projects have reached commercial and financial close, they will enter into the construction period which is expected to be 24 months. The new generation capacity should therefore be online from 2025.

With the signing of these 13 agreements, the Department has now concluded 19 out of the 25 announced projects under Bid Window 5, which will add an overall total of 1 759MW renewable capacity to the national grid. This comprises 784 MW from onshore wind technologies and 975 MW from Solar PV.

At the end of October 2022, which was the cut-off date communicated by the Department, the 6 remaining Preferred Bidders appointed under Bid Window 5 indicated that they were not ready to close. The Department is in discussions with these Preferred Bidder projects to conclude the procurement within the framework of the Request for Proposals (RFP) and the law.

The total investment attracted from all 19 projects that have signed to date under Bid Window 5 is R34.3 billion, which is a substantial input into our economy. The 19 signed projects will contribute a total of 7 701 job year opportunities in the construction and operation of these power plants.

As with other IPP procurement, Bid Window 5 was also designed to stimulate economic growth and support socio-economic transformation throughout the full value chain. In this respect, the bid window achieved an overall 49.2% South African ownership, of which the total BBBEE ownership amounts to 36.2%. A percentage of the total project spend will be retained for local suppliers, encouraging the growth of the local industry. The minimum local content commitments by the Bid Window 5 IPPs amount to 46% of total project value during construction, and 42% during operation.

All the signed Bid Window 5 projects will also contribute over R1.9 billion on Skills Development, Supplier Development, Enterprise Development, and Socio-Economic Development in the communities in which they operate.

REIPPPP Bid Window 6

During the event, Minister Mantashe also announced the Preferred Bidders appointed under the 6th Bid Window of the REIPPPP. The bid window was released in April 2022, and 56 bid submissions were received on 3rd October 2022. Following the evaluation, the Minister today announced that five (5) Solar PV projects have been appointed as Preferred Bidders, at a total of 860MW. An eligible 6th bidder has also been identified, and the Department is in discussion with the potential bidder on conditions for appointment, in order to fill the remaining gap up to 1000MW.

The five announced Preferred Bidders are as follows:

Project Name

Contracted Capacity (MW)

Price

Province

Kutlwano Solar Power Plant

150,00

469,50

North West

Boitumelo Solar Power Plant

150,00

469,50

North West

Virginia Solar Park

240,00

486,50

Free State

Good Hope Solar Park

200,00

498,90

Free State

Doornhoek PV

120,00

540,00

North West

These 5 projects have achieved a weighted average tariff of R490.48 which is an 8% increase from the tariffs achieved for Solar PV technologies during Bid Window 5 (R454.23). This is indicative of the global economic challenges experienced over the last two years resulting in increased input costs across the entire value chain. The total investment attracted through the 5 projects is R12.1 billion. The total BBEEE shareholding commitment is 49% whilst the local content commitment is 46.4% of total project cost. These 5 projects will attract a total of 4556 job years for South African citizens during construction and operations. The total Economic Development commitments made by these projects over the lifetime of the projects amount to over R790 million.

The Department received Onshore Wind bid responses amounting to 4 116 MW for the Bid Window 6, all of which are located in the Eastern Cape and Western Cape supply areas. Following the confirmation from Eskom during the evaluation that no grid capacity was available to connect any proposed Onshore Wind projects in these supply areas, the Department could unfortunately not award any of the wind projects up to the allocated 3 200 MW under this bid window.

Minister Mantashe emphasised that the Department is engaging with Eskom to find ways around the grid challenges, especially considering that the National Energy Regulator of South Africa is currently considering a Determination for 14 791 megawatts (MW) of new generation capacity. It is critical that the grid accommodates this additional generation capacity. The Cape supply region remains the most attractive area for development of wind and solar projects and is also the area where we have historically achieved the cheapest prices. However, the Minister encouraged project developers to consider developing projects in other parts of the country where there is still capacity, whilst the country builds additional grid capacity in the cape supply area.

Background to the REIPPPP Bid Windows 5

The REIPPPP Bid Window 5 Request for Proposals (RFP) was released on 12th April 2021 and was the first bid window to be launched under the Ministerial Determination promulgated on 25th September 2022 under IRP2019. The bid window aims to procure a total of 2 600MW energy, consisting of 1 600 MW onshore wind and 1000MW Solar PV plants.

The Department received 102 bids during bid submission on 16th August 2021 totaling an oversubscribed 9 644 MW. The Minister announced 25 Preferred Bidders on the 28th October 2021, to provide a total capacity of 2 583 MW. Of this, 1608 MW will be procured from 12 Wind projects, and 975 MW from 13 Solar PV projects.

The agreements that were signed on 10th November 2022, include:

  • The Power Purchase Agreement (PPA): This agreement regulates the sale of the energy between the respective IPPs and Eskom. This document will be signed by Eskom and the IPPs.
  • The Implementation Agreement (IA): The IA includes all the commitments made by the bidders in terms of Socio-economic Development, Enterprise Development, etc. In addition, the IA also provides for the required Government support to the IPPs and the lenders to the project. This document will be signed by the Department and the IPPs; and
  • The Direct Agreement (DA): This agreement allows the lenders to have step-in rights, in the event the IPPs fail to honour its obligations under the Finance Agreement. This enables the lender to take over the plant(s) and/or hand it over to another party to operate the plant(s) on its behalf until the lender has recovered the total amount invested on the respective project. This agreement is signed by the Department, Eskom, IPPs and Lenders.

 

Following the conclusion of the REIPPPP Bid Window 5 procurement, the following overall outcomes have been achieved under this Bid Window:

 

Projects announced at Preferred Bidder stage

25 projects at a total of 2583MW

1 608MW

from Onshore Wind

975MW

from Solar PV

 

Total  number  of  projects  that  have  signed agreements

19 projects at a total of 1 759MW

784 MW

from Onshore Wind

975MW

from Solar PV

Total investment attracted

R34,3 billion

Total      jobs     that      will     be     created      during construction and operations

7 701 job years

(i.e full time job opportunities created over 1 year for 1 person)

Committed to be spent on Skills Development, Supplier Development, Enterprise Development, and Socio-Economic Development over  the lifetime of the projects.

 

R1.9 billion

Background to the REIPPPP Bid Windows 6

The sixth round of the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP Bid Window 6), is the second bid window to be procured in response to the Second Ministerial Determination. The Bid Window called for new generation capacity of 4 200MW, made up of 3200 MW wind energy resources and 1000 MW Solar Photovoltaic energy resources

Key milestones achieved in respect of the procurement process are as follows:

  • Ministerial Determination Gazetted on 25th September 2021;
  • Request for Proposals (RFP) released to market on 6th April 2022;
  • Bidders’ Conference was held on 7 July 2022;
  • Updated  Request  for  Proposals  (RFP)  advertisement  to  increase  MW  and  extend timetable on 8th September 2022
  • Bid Submission Date on 3rd October 2022;
  • Bid Evaluation commenced on 5th October 2022
  • Preferred Bidders announced on 8th December 2022
     

Enquries email: mediadesk@energy.gov.za / media@dmre.gov.za

Share this page

Similar categories to explore