The City of Tshwane (CoT) in partnership with the Department of Water and Sanitation (DWS) and Magalies Water (MW), acknowledges the concerns raised by the Hammanskraal community, particularly in areas such as Majaneng (east of Makapanstad Road), Kudube Units 1, 2, 3, 6, 10 and Unit D, Jubilee Tower, Jubilee Direct, and Dominican Tower. These concerns relate to the ongoing inconsistent water supply in the phase two targeted area.
The DWS handed over Module 2 of the Klipdrift Water Treatment Works on 29 June 2025 to City of Tshwane. Module 2 is designed to supply 12.5 ML of water per day.
Due to unanticipated delays in completing the permanent pipeline to take water from Babelegi to Temba, an alternative, older pipeline was used to deliver water in the interim. However, this pipeline has experienced setbacks due to frequent leaks and delivery of lesser volumes than anticipated.
The project partners – Magalies Water Board, the City of Tshwane, and the Department of Water and Sanitation – have resolved to expedite the completion of the main planned pipeline. In the meantime, the old temporary pipeline is still being used to provide what is likely to be an intermittent water supply for flushing purposes.
To cover the shortfall, the City of Tshwane has made available additional water tankers. A detailed schedule for water tanker availability per area will be shared with the community to ensure continued access to water while the permanent pipeline is being completed.
To address these challenges and improve the water supply to the affected areas – with the aim of restoring water supply by the second week of August 2025 – the following actions are being undertaken:
-
Permanent supply line from Babelegi to Temba Reservoir 3
The permanent pipeline is on track for completion. Once completed, it will allow for a more stable and higher volume of water to be delivered. Water supply to the community through this route will be fully utilised after final testing confirms the water is safe to use and the pipeline is fit for transporting water. -
Improving the temporary Bosplaas line
The Bosplaas pipeline is currently delivering an average of 6.3 million litres per day, which is not enough to complete the system flushing process. The technical team is working on adjusting the system to deliver improved volumes while working on completing the pipeline. These adjustments will help the system work more efficiently and effectively. -
Water quality testing and flushing
The process of cleaning and testing the water system is now over 90% complete and should be completed as soon as there is sufficient water to conclude the flushing. A week would be sufficient.
Some residents have asked for the old water supply from Temba Water Treatment Works to be restored while waiting for increased volume. However, doing so would reverse the progress made to date and delay the completion of the flushing process to around mid-September 2025.
The water currently being produced by the two modules meets the minimum safety standards (SANS 241:2015) and is being used to clean the system. However, residents in Module 2 are advised not to drink the water from their taps until official communication confirms the safe consumption and use of the water.
We recognise the seriousness of the situation and assure the Hammanskraal community that all reasonable efforts are being made to restore a consistent and safe water supply. We sincerely apologise for the inconvenience and hardship caused by these challenges.
Enquiries:
City of Tshwane: Samkelo Mgobozi
Divisional Head: Mayoral Spokesperson
Cell: 078 231 5977
Email: sammgobozi@tshwane.gov.za
Magalies Water: David Magae
Manager: Communications and Media Relations
Cell: 082 761 3456
Email: davidmag@magalieswater.co.za
Department of Water and Sanitation: Wisane Mavasa
DWS Spokesperson
Cell: 060 561 8935
Email: mavasaw@dws.gov.za
#ServiceDeliveryZA